MABS Institution
11th Business Maths Weekly Test - 1 ( Operations Research )-Aug 2020
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Construct a network diagram for the following situation:
A<D,E; B, D<F; C<G and B<H. -
Solve the following LPP graphically. Maximize \(Z={ x }_{ 1 }+{ x }_{ 2 }\)
Subject to the constraints \({ x }_{ 1 }-{ x }_{ 2 }\le -1,{ -x }_{ 1 }+{ x }_{ 2 }\le 0\quad and\quad { x }_{ 1 }+{ x }_{ 2 }\ge 0\) -
Solve the following LPP graphically.\(Maximize\quad Z=-{ x }_{ 1 }+2{ x }_{ 2 }\)
Subject to the constraints \(-{ x }_{ 1 }+3{ x }_{ 2 }\le 10,\quad { x }_{ 1 }+{ x }_{ 2 }\le 6,\quad { x }_{ 1 }{ -x }_{ 2 }\le 2\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\) -
-
Solve the following LPP graphically. Minimize \(Z={ x }_{ 1 }-5{ x }_{ 2 }+20\)
Subject to the constraints \({ x }_{ 1 }-{ x }_{ 2 }\ge 0,\quad { -x }_{ 1 }+2{ x }_{ 2 }\ge 2,\quad { x }_{ 1 }\ge 3,{ x }_{ 2 }\le 4\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\) -
Solve the following LPP graphically.
Maximize \(Z=6{ x }_{ 1 }+5{ x }_{ 2 }\) Subject to the constraints \(3{ x }_{ 1 }+5{ x }_{ 2 }\le 15,\quad 5{ x }_{ 1 }+2{ x }_{ 2 }\le 10\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\)
-
-
Solve the following LPP graphically. Minimize\(Z=-3{ x }_{ 1 }+4{ x }_{ 2 }\)
Subject to the constraints \({ x }_{ 1 }+2{ x }_{ 2 }\le 8\quad ,{ 3x }_{ 1 }+{ 2x }_{ 2 }\le 12\quad and\quad \quad { x }_{ 1 }\ge 0,{ x }_{ 2 }\ge 2.\) -
A dietician wishes to mix two types of food F1 and F2 in such a way that the vitamin contents of the mixture contains atleast 6units of vitamin A and 9 units of vitamin B. Food F1 costs Rs.50 per kg and F2 costs Rs 70 per kg. Food F1 contains 4 units per kg of vitamin A and 6 units per kg of vitamin B while food F2 contains 5 units per kg of vitamin A and b units per kg of vitamin B. Formulate the above problem as a linear programming problem to minimize the cost of mixture.
-
Solve the following linear programming problem graphically.
Maximize Z = 3x1 + 5x2 subject to the constraints x1+x2≤6, x1≤4; x2≤5, and x1, x2 ≥0 -
The following table gives the activities of a project and their duration in days
Activity 1-2 1-3 2-3 2-4 3-4 3-5 4-5 Duration 5 8 6 7 5 4 8 Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
-
-
The following table gives the characteristics of project
Activity 1-2 1-3 2-3 3-4 3-5 4-6 5-6 Duration (in days) 5 10 3 4 6 6 5 Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
-
A firm manufactures pills in two sizes A and B. Size A contains 2 mgs of aspirin, 5 mgs of bicarbonate and 1 mg of codeine. Size B contains 1 mg. of aspirin, 8 mgs. of bicarbonate and 6 mgs. of codeine. It is found by users that it requires atleast 12 mgs. of aspirin, 74 mgs.of bicarbonate and 24 mgs. of codeine for providing immediate relief. It is required to determine the least number of pills a patient should take to get immediate relief. Formulate the problem as a standard LLP.
-