The following table use the activities in a building project.
Activity |
1-2 |
1-3 |
2-3 |
2-4 |
3-4 |
4-5 |
Duration (days) |
21 |
26 |
11 |
13 |
5 |
11 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.