MABS Institution
11th Business Maths Monthly Test - 1 ( Operations Research )-Aug 2020
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Construct a network diagram for the following situation:
A<D,E; B, D<F; C<G and B<H. -
Draw a network diagram for the project whose activities and their predecessor relationships are given below
Activity A B C D E F Predecessor activity - - D A B C -
A producer has 30 and 17 units of labour and capital respectively which he can use to produce two types of goods X and Y. To produce one unit of X, 2 unit of labour and 3 units of capital are required. Similarly, 3 units of labour and 1 unit of capital is required to produce one unit of Y. If X and Yare priced at HOO and H20 per unit respectively, how should the producer use his resources to maximize the total revenue? Formulate the LPP for the above.
-
Solve the following LPP graphically. \(\\ \therefore \quad Maximize\quad Z=3{ x }_{ 1 }+4{ x }_{ 2 }\)
subject to the constraints \({ x }_{ 1 }+{ x }_{ 2 }\le 4\quad \quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\) -
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
Immediate Predecessor A B C D E F G H I Activity B C D,E,F G I H J K L -
Solve the following LPP graphically, Minimize \(Z=3{ x }_{ 1 }+5{ x }_{ 2 }\)
Subject to the constraints \({ x }_{ 1 }+3{ x }_{ 2 }\ge 3,\quad { x }_{ 1 }+{ x }_{ 2 }\ge 2\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0.\) -
Solve the following LPP graphically.\(Maximize\quad Z=-{ x }_{ 1 }+2{ x }_{ 2 }\)
Subject to the constraints \(-{ x }_{ 1 }+3{ x }_{ 2 }\le 10,\quad { x }_{ 1 }+{ x }_{ 2 }\le 6,\quad { x }_{ 1 }{ -x }_{ 2 }\le 2\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\) -
A soft drink company has two bottling plants C1 and C2. Each plant produces three different soft drinks S1, S2 and S3. The production of the two plants in number of bottles per day are:
Product Plant C1 C2 S1 3000 1000 S2 1000 1000 S3 2000 6000 A market survey indicates that during the month of April there will be a demand for 24000 bottles of S1, 16000 bottles of S2 and 48000 bottles of S3. The operating costs, per day, of running plants C1 and C2 are respectively Rs.600 and Rs.400. How many days should the firm run each plant in April so that the production cost is minimized while still meeting the market demand? Formulate the above as a linear programming model.
-
-
Solve the following LPP graphically.
Maximize \(Z=6{ x }_{ 1 }+5{ x }_{ 2 }\) Subject to the constraints \(3{ x }_{ 1 }+5{ x }_{ 2 }\le 15,\quad 5{ x }_{ 1 }+2{ x }_{ 2 }\le 10\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\) -
Solve the following LPP graphically. Minimize \(Z={ x }_{ 1 }-5{ x }_{ 2 }+20\)
Subject to the constraints \({ x }_{ 1 }-{ x }_{ 2 }\ge 0,\quad { -x }_{ 1 }+2{ x }_{ 2 }\ge 2,\quad { x }_{ 1 }\ge 3,{ x }_{ 2 }\le 4\quad and\quad { x }_{ 1 },{ x }_{ 2 }\ge 0\)
-
-
Solve the following LPP graphically. Minimize\(Z=-3{ x }_{ 1 }+4{ x }_{ 2 }\)
Subject to the constraints \({ x }_{ 1 }+2{ x }_{ 2 }\le 8\quad ,{ 3x }_{ 1 }+{ 2x }_{ 2 }\le 12\quad and\quad \quad { x }_{ 1 }\ge 0,{ x }_{ 2 }\ge 2.\) -
Develop a network based on the following information.
Activity A B C D B E Immediate Predecessor - - A C E F
-
Solve the following LPP graphically. Maximize \(Z={ x }_{ 1 }+{ x }_{ 2 }\)
Subject to the constraints \({ x }_{ 1 }-{ x }_{ 2 }\le -1,{ -x }_{ 1 }+{ x }_{ 2 }\le 0\quad and\quad { x }_{ 1 }+{ x }_{ 2 }\ge 0\) -
Solve the following LPP. Maximize Z = 2 x1 +5x2 subject to the conditions x1+ 4x2 ≤ 24. 3x1+x2 ≤ 21, x1+x2 ≤ 9 and x1, x2 ≥ 0.
-
Every gram of wheat provides 0.1 g of proteins and 0.25 g of carbohydrates. The corresponding values of rice are 0.05 g and 0.5 g respectively. Wheat cost Rs.4 per kg and rice cost Rs.6 per kg. The minimum daily requirements of proteins and carbohydrate for an average child are 50 g and 200 g respectively. In what quantities should wheat and rice be mixed in the daily diet to provide minimum daily requirements of proteins and carbohydrate at minimum cost. Frame an LPP and solve it graphically.
-
A Project has the following time schedule
Activity 1-2 2-3 2-4 3-5 4-6 5-6 Duration (in days) 6 8 4 9 2 7 Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
-
A dietician wishes to mix two types of food F1 and F2 in such a way that the vitamin contents of the mixture contains atleast 6units of vitamin A and 9 units of vitamin B. Food F1 costs Rs.50 per kg and F2 costs Rs 70 per kg. Food F1 contains 4 units per kg of vitamin A and 6 units per kg of vitamin B while food F2 contains 5 units per kg of vitamin A and b units per kg of vitamin B. Formulate the above problem as a linear programming problem to minimize the cost of mixture.
-
The following table gives the characteristics of project
Activity 1-2 1-3 2-3 3-4 3-5 4-6 5-6 Duration (in days) 5 10 3 4 6 6 5 Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
-
A Project has the following time schedule
Activity 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 Duration(in days) 7 6 14 5 11 7 11 4 18 Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
-
-
One kind of the cake requires 200 g of flour and 25 g of fat, and another kind of cake requires 100 g of flour and 50 g of fat. Find the maximum number of cakes which can be made from 5 kg of flour and 1 kg of fat assuming that there is no shortage of other ingredients used in making the cakes?
-
Solve the following linear programming problem graphically.
Maximise Z=4x1+x2 subject to the constraints x1+x2≤50; 3x1+x2≤90 and x1≥0, x2≥0.
-
-
A manufacturer produces two types of steel trunks. He has two machine A and B. For completing, the first type of the trunk requires 3 hours on machine A and 2 hours on machine B, whereas the second type of the trunk requires 3 hours on machine A and 3 hours on machine B. Machines A and B can work at the most for 18 hours and 14 hours per day respectively. He earns a profit of Rs.30 andRs.40 per trunk of the first type and second type respectively. How many trunks of the each type must he make each day to make maximum profit?
-
Solve the following linear programming problems by graphical method.
(i) Maximize Z = 6x1 + 8x2 subject to constraints 30x1+20x2≤300; 5x1+10x2≤110; and x1, x2 > 0.
(ii) Maximize Z =22x1+ 18x2 subject to constraints 960x1+ 640x2≤15360; x1≥ x≤20 and x1, x2 ≥0.
(iii) Minimize Z= 3x1+ 2x1 subject to the constraints 5x1+ x2≥10; x1+x2≥6; x1+ 4, x2 ≥12 and x1, x2≥0.
(iv) Maximize Z= 40x1+ 50x2 = subject to constraints 30x1+x2≤9; x1+2x2≤8 and x1, x2≥0
(v) Maximize Z= 20x1+30x2 subject to constraints 3x1+3x2≤36; 5x1+2x2≤50; 2x1+6x2≤60 and x1,x2
(vi) Minimize Z=20x1+40x2 subject to the constraints 36x1+ 6x2≥108, 3x1+12x2≥36, 20x1+10x2≥100 and x1,x2≥0.